Southeast Market Pipelines Project Certificate Vacated and Remanded to FERC for Further Environmental Review on Greenhouse Gas Emissions

In a 2-1 decision that issued today, the U.S. Court of Appeals for the District of Columbia Circuit (D.C. Circuit) in Sierra Club et. al v. Federal Energy Regulatory Commission (Sierra Club) vacated and remanded a Natural Gas Act (NGA) Section 7 certificate of public convenience and necessity granted by the Federal Energy Regulatory Commission (FERC) to the Southeast Market Pipelines Project (Project) in 2016.  The Project comprises three natural gas pipelines currently under construction in Alabama, Georgia, and Florida that, once built, will transport over 1 billion cubic feet of natural gas per day over 500 miles to feed new and existing natural gas-fired electric plants in Florida and to serve the growing natural gas demand of Florida utility customers.  (more…)